S
Steve Chermak
I am fairly new to Project but have been asked to look into a problem that
the people who have been working with it for a while have not been able to
figure out, that they are having with some of their MS Project workbooks.
There are separate workbooks to track work done in different geographical
areas of our state.
On a couple of them the cost field recalculates on some tasks when the
Percent Complete field is changed, and they do not want that to happen.
The "Actual Costs are calculated by Project" check box is enabled in the
calculation tab of the Options.
I took one of the workbooks and went through some of the tasks myself, and
found a few where this occurred.
There are two quirks to this problem:
1. Within the same workbook, this problem does not occur on most of the
tasks, only on a few.
2. This happened only the first time I changed the percent complete (on a
task where the problem occurred). After that it did not happen, even if I
saved the workbook and re-opened it again.
I double clicked on some of these tasks to see what resources made up the
task, and I could not find anything that stood out as a glaring difference or
consistent difference between tasks where the problem occurred and ones where
the problem did not.
The cost field appears to be a summation of all the resources for any given
task. The people using these workbooks do not intend to enter any cost data
manually into the field, except when they entered the values originally for
the resources.
I looked at the resource sheet and resource usage sheet, and nothing stood
out in those views either.
If somebody could point me towards what things could possibly cause this
and/or what things I should investigate about the settings or about the data
that might lead to the answer, I would appreciate it.
Thank you
the people who have been working with it for a while have not been able to
figure out, that they are having with some of their MS Project workbooks.
There are separate workbooks to track work done in different geographical
areas of our state.
On a couple of them the cost field recalculates on some tasks when the
Percent Complete field is changed, and they do not want that to happen.
The "Actual Costs are calculated by Project" check box is enabled in the
calculation tab of the Options.
I took one of the workbooks and went through some of the tasks myself, and
found a few where this occurred.
There are two quirks to this problem:
1. Within the same workbook, this problem does not occur on most of the
tasks, only on a few.
2. This happened only the first time I changed the percent complete (on a
task where the problem occurred). After that it did not happen, even if I
saved the workbook and re-opened it again.
I double clicked on some of these tasks to see what resources made up the
task, and I could not find anything that stood out as a glaring difference or
consistent difference between tasks where the problem occurred and ones where
the problem did not.
The cost field appears to be a summation of all the resources for any given
task. The people using these workbooks do not intend to enter any cost data
manually into the field, except when they entered the values originally for
the resources.
I looked at the resource sheet and resource usage sheet, and nothing stood
out in those views either.
If somebody could point me towards what things could possibly cause this
and/or what things I should investigate about the settings or about the data
that might lead to the answer, I would appreciate it.
Thank you