I feel your pain, we have 61 resources. However, without using a VBA macro
there is not going to be an easy way to do it. Remember, each resource has
its own rate schedules and effective dates for those rates. As such, you
need to enter a date and a rate in the Cost Table B.
What I did for one client was design a custom user form. The form allowed
me to loop through each resource (a For Each loop). I hard coded the date as
"today" and then had it prepopulate the new rate with the old rate plus a
factor into two text boxes on the form. I then could just make some quick
changes to the rate and hit the Save/Next button. The "save" put the
information into Cost Rate Table B with the effective date.
In all reality, it took me just as long to develop the form as it would to
hand crank it into the rate table.
Unfortunately, I do not have ready access to this code. To invent the form
for you would be billable hours.
As an alternative, a colleague of mine tried to export the mpp file to
Access and make the changes there. However, the effective dates and rates
are not located conveniently together in a table to make this effort
worthwhile either.
--
If this post was helpful, please consider rating it.
Jim
It''s software; it''s not allowed to win.
Visit
http://project.mvps.org/ for FAQs and more information
about Microsoft Project