J
Johnnie
Currently project defauls to Tab A in the cost rate table column when
creating new schedules or adding new resources to an existing schedule. Is
it possible to change the default so that when a new resource is added, the
Cost Rate will not default to Tab A (i.e, b, or c)? As we have various
projects and we charge different amounts, it is not possible to alterate the
costs in the tabs.
We are using Project Server 2003. Thanks for your help.
Johnnie
creating new schedules or adding new resources to an existing schedule. Is
it possible to change the default so that when a new resource is added, the
Cost Rate will not default to Tab A (i.e, b, or c)? As we have various
projects and we charge different amounts, it is not possible to alterate the
costs in the tabs.
We are using Project Server 2003. Thanks for your help.
Johnnie