Cost Rate Tables - Renaming

D

dee

Hi,

Is it possible to assign names to cost tables for a resource. Instead of A,
B, etc., I would like to see names that are more clear and meaningful.
 
J

JulieS

Hi Dee,

As far as I know, no. The rate table names are "hard coded" into the product.

I hope this helps. Let us know how you get along.

Julie
 
D

dee

That's a shame... how do you know what A means or B means when selecting
their rate? Any ideas?
 
J

Jim Aksel

Add a note in the notes field to explain what you mean for A, B, C ...
We do this because we apply different rates in different facilities. Also,
we may charge different rates to different tiers of customers.
 
M

Mike Glen

Hi Dee,

You did set the rates yourself? Double click on a resource name in the
Resource sheet view, and in the dialog select the Cost tab and then the Rate
you need.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 
E

engineer12345

Hello ,
I entered cost values in table A and table B as real cost (A) and selling
price (B) and i dont know how to use it and show on grand chart
Best Regards
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question