T
tmorr16
I am using MS Project 2003. I am attempting to create a highlevel
project plan that includes the highlevel summary task from several
other project plans. I know how to link tasks between separate
projects, but I don't want to show two task for the same tas, although
one is grayed out. I just want to show one with the %complete. In
addition, I want to add resources at the level and I didn't want to
have the extra tasks with no resources.
I hope this makes, sense, but if not, I can add more clarity.
Terry J. Morris
project plan that includes the highlevel summary task from several
other project plans. I know how to link tasks between separate
projects, but I don't want to show two task for the same tas, although
one is grayed out. I just want to show one with the %complete. In
addition, I want to add resources at the level and I didn't want to
have the extra tasks with no resources.
I hope this makes, sense, but if not, I can add more clarity.
Terry J. Morris