M
Mark E
Hello,
I have been creating 'basic' formulas using Enterprise Custom Project
Fields. I have been somewhat successful until now.
I have created a custom field called "Average Project Rate". I am using
the following formula:
[Enterprise Project Cost1]/[Baseline Work]
Please note: Enterprise Project Cost1 is a custom field called "Contract
Value". The PM will enter in the contract value when the schedule is first
created.
The sample I have setup will not calculate the above formula correctly:
Project1:
Enterprise Project Cost1 = $100.00
Baseline Work = 5 hrs
Contract Value = 0.33
I am not sure how it is calculating 0.33 within the "Contract Value" Field.
The value should be $20.00.
I was fooling around with the formula to try and understand how it works. I
tried [Contract Value] / [Baseline Cost] and this calculated correctly.
What am I missing or not doing???? Any feedback will be helpful!
Mark Etheridge
PMP
I have been creating 'basic' formulas using Enterprise Custom Project
Fields. I have been somewhat successful until now.
I have created a custom field called "Average Project Rate". I am using
the following formula:
[Enterprise Project Cost1]/[Baseline Work]
Please note: Enterprise Project Cost1 is a custom field called "Contract
Value". The PM will enter in the contract value when the schedule is first
created.
The sample I have setup will not calculate the above formula correctly:
Project1:
Enterprise Project Cost1 = $100.00
Baseline Work = 5 hrs
Contract Value = 0.33
I am not sure how it is calculating 0.33 within the "Contract Value" Field.
The value should be $20.00.
I was fooling around with the formula to try and understand how it works. I
tried [Contract Value] / [Baseline Cost] and this calculated correctly.
What am I missing or not doing???? Any feedback will be helpful!
Mark Etheridge
PMP