T
Tito
Hello all!
We recently transitioned to Project Server and haven't figured out the
Project Server equivalent of creating monthly snapshots for archiving
purposes and how best to share our data with people outside of the network.
In the past if we needed to create a month-end snapshot of the schedules we
simply created a folder and copied the entire contents of the current folder
into a folder we created for purposes of archiving. Now that our data is in
Server we're unsure on how best to do this....
We also have the task of sharing our data with external auditors on a montly
basis but whenever we create an MPP version of our Server data we lose all of
the Lookup Table data.
Some background on our environment:
-We use consolidated schedules extensively and have tons of dependencies
across the subprojects.
-We use calculated fields and lookup tables.
-Our subprojects range from 500-2K activities so our consolidated schedules
are typically in the range of 15K activities.
-Only some of the schedules are resource loaded.
-We recently installed SP1 for Project Server 2007.
I would greatly appreciate any help on the above questions.
We recently transitioned to Project Server and haven't figured out the
Project Server equivalent of creating monthly snapshots for archiving
purposes and how best to share our data with people outside of the network.
In the past if we needed to create a month-end snapshot of the schedules we
simply created a folder and copied the entire contents of the current folder
into a folder we created for purposes of archiving. Now that our data is in
Server we're unsure on how best to do this....
We also have the task of sharing our data with external auditors on a montly
basis but whenever we create an MPP version of our Server data we lose all of
the Lookup Table data.
Some background on our environment:
-We use consolidated schedules extensively and have tons of dependencies
across the subprojects.
-We use calculated fields and lookup tables.
-Our subprojects range from 500-2K activities so our consolidated schedules
are typically in the range of 15K activities.
-Only some of the schedules are resource loaded.
-We recently installed SP1 for Project Server 2007.
I would greatly appreciate any help on the above questions.