Hi,
I have a critical path error problem, hoping someone can answer.
When looking at the citical path, the critical path does not show up only
parts of the critical path shows up. If you play with the durations of some
tasks you may get the real critical path. This is with all task ASAP, no
other constaints and with the tasks set to fixed work effort driven.
I can find the critical path by using the trace predecessors & successors
marco written by Jack Dahgren (which by the way is an awesome macro if you
are not using it I highly suggest you do ) This macro clearly shows the items
on the critical path. When I set theProject to a fixed duration, not effort
driven and remove all the work, the true critical path shows up. (same items
using the macro)
I have a critical path error problem, hoping someone can answer.
When looking at the citical path, the critical path does not show up only
parts of the critical path shows up. If you play with the durations of some
tasks you may get the real critical path. This is with all task ASAP, no
other constaints and with the tasks set to fixed work effort driven.
I can find the critical path by using the trace predecessors & successors
marco written by Jack Dahgren (which by the way is an awesome macro if you
are not using it I highly suggest you do ) This macro clearly shows the items
on the critical path. When I set theProject to a fixed duration, not effort
driven and remove all the work, the true critical path shows up. (same items
using the macro)