Critical Path in Tracking Gantt

R

Rod Gill

The default Tracking Gantt View already shows critical tasks in red and
non-critical in blue. if you have a milestone as the last task to finish and
it has a constraining date, then you will see no red task bars.

--

Rod Gill
Project MVP
Visit www.msproject-systems.com for Project Companion Tools and more

NEW!! Project VBA Book now in stock, for details visit:
www.projectvbabook.com
 
S

sarah

Sorry I think i should have phrase my question better.

Is it possible to see the relationship line in a Tracking Gantt? Currently
i am switching between Gantt Chart View and the Tracking Gantt View and was
wondering if there is anyway to put the task relationship line in a Tracking
Gantt view.
 
R

Rod Gill

Format, Layout with the Tracking Gantt view active. Then choose the line
style you want. This is on by default so someone must have turned it off!

--

Rod Gill
Project MVP
Visit www.msproject-systems.com for Project Companion Tools and more

NEW!! Project VBA Book now in stock, for details visit:
www.projectvbabook.com
 