There is really no standard set of milestones that must exist in every
project, other than the recommended practice of always having a "start"
and "finished" milestone, so it would be hard to answer your specific
question. Other than start and finish, everything else is a judgement
call, the milestones indicating some noteworthy events that take place
during the project. The "critical path" is defined as that sequence of
tasks and events that determines the project duration - if anything on it
is delayed, the project finish is delayed. But "critical" doesn't have
anything to do with "importance." If you track the completion of key
deliverables with milestones, as in very commonly done, and yo have
several parallel chains of tasks running through the project, only those
deliverables that lie on the longest path are critical. Thus any
milestones that occur on the other paths are non-critical, by definition.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://project.mvps.org/faqs.htm for the FAQs
Vijay said:
Hi Jan,
Just one more help. Can you please let me know some important milestones
which need not be on critical path. I feel we there should be no issue in
having some milestones out of critical path.
But my manager feels all the milestones should be on critical path and he
is
asking me for specific examples. Request you to share if you have
any..and i
will also find out..
Thanks for ur help.