Critical Path Network

D

Declan

Is it posible to create a CPN diagram using events and activities in project
2003, where the task (or activitiy) would actually be displayed on the
connecting line, meaning there would be no need for duplicate lines coming
out of each box.
 
J

JulieS

Hello Declan,

I think you are looking for an AOA (activity on arrow) diagram.
Sorry, Project does not provide such a view.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
D

davegb

Is it posible to create a CPN diagram using events and activities in project
2003, where the task (or activitiy) would actually be displayed on the
connecting line, meaning there would be no need for duplicate lines coming
out of each box.

Not sure what you mean by "duplicate lines coming out of each box". If
you're looking for AOA, as Julie said, Project doesn't have this
capability.
 
D

Declan

thanks julieS

JulieS said:
Hello Declan,

I think you are looking for an AOA (activity on arrow) diagram.
Sorry, Project does not provide such a view.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 