J
johnston
Can someone recommend a source that offers a comprehensive explanation about
how MS Project 2003 determines the critical path? I have stumbled over
several instances that make no sense to me. As an example, in one case four
tasks were linked in series FS, but only the first and fourth task were on
the critical path. As another example, I had entered a duration of 7 emonths
that had a slack time of 0.1 emonths, which I assume would be about 3 days.
Later I changed the critical path calculation to count as critical any task
that had five or less days of slack, but the task still did not appear on
the critical path.
how MS Project 2003 determines the critical path? I have stumbled over
several instances that make no sense to me. As an example, in one case four
tasks were linked in series FS, but only the first and fourth task were on
the critical path. As another example, I had entered a duration of 7 emonths
that had a slack time of 0.1 emonths, which I assume would be about 3 days.
Later I changed the critical path calculation to count as critical any task
that had five or less days of slack, but the task still did not appear on
the critical path.