Custom field for summary task

P

Perl

Hello,

I created an enterprise custom text field. Project manager fill this field
manually.
Resource see the field at the task page at PWA.
But if a project manager fill the field for a summary task, the resource
can't see the data at the timesheet.
I don't want to assign resource to summary.

Any idea ?

Perl
 
B

Ben Howard

Hi Perl,
I you'll need to fill the field out at the task level, not at the summary
task level.
 