Custom Field to extract Summary Task information

J

JeffT

It's easy to extract current date/cost/duration information for a particular
flagged task. However, when that task is a Summary Task, the custom field
won't grab the information.

For instance, we have a TOLC value Design Phase
Our Template has a set of tasks UNDER Design Phase
I'm trying to get a Summary Task to grab that information and roll it up for
project center views, but no luck.
Right now I have to do it with Macros. I know there are other ways, just
hoping
somebody knows how to grab Summary Task information into a custom field.
 
J

Jan De Messemaeker

Hi,

The customize field form allows you to set a rule for the summary tasks.
Hope this helps,
 

Ask a Question