R
R Casali
Good Afternoon,
The project plan that I am working on has a field ("text2") that has been
set to capture one of about eight (8) project sub-codes, for the purposes of
time tracking. This field is on the individual task level.
I would like to be able to tie each resource name to the relevant project
sub-codes, then to the sum of the work associated with all of the tasks
sharing the same subcode.
This is essestially the Resource Usage View, with the individual tasks
grouped by my project sub-code fields.
Any ideas? Thank you and have a great day!
The project plan that I am working on has a field ("text2") that has been
set to capture one of about eight (8) project sub-codes, for the purposes of
time tracking. This field is on the individual task level.
I would like to be able to tie each resource name to the relevant project
sub-codes, then to the sum of the work associated with all of the tasks
sharing the same subcode.
This is essestially the Resource Usage View, with the individual tasks
grouped by my project sub-code fields.
Any ideas? Thank you and have a great day!