Customize timesheet

M

Manmeet Chaudhari

Hi
I want to allow my team members to edit the finish date when they are
updating their activities. how ever i noticed in published fields finish date
is not available.

Please suggest me some work around such that i can allow my resource to
change the finish date. This is very critical for me

Thanks
 
M

Manmeet Chaudhari

Thanks a lot for ur response
Can you plese help me with the macro as well
 
D

Dale Howard [MVP]

Manmeet --

If they increase the Remaining Work, the software will adjust the Finish
date accordingly. Hope this helps.
 