date range missing

M

Majid

Hello Dear,
Somehow the date range is not appered in the "filter for" drop down.
I hvae tried to add it using the organizer but was no luck.
Please advise, thank you Majid
 
J

John

Majid said:
Hello Dear,
Somehow the date range is not appered in the "filter for" drop down.
I hvae tried to add it using the organizer but was no luck.
Please advise, thank you Majid

Majid,
If you go to Project/Filtered for/More filters does the Date Range
filter appear in the selection list?

John
Project MVP
 
J

John

Majid said:
No John
I see only "all tasks","critical tools PERT", and "using resources..."

Majid,
Something has apparently happened to Global file if you only have 3 of
the default filters. Here are a couple of things to try. First, go to
Help/Detect and Repair.

If that doesn't restore the filters, you can trash your active Global
and Project will create a new one, hopefully with all the default stuff.
Before trashing your existing Global however, you need to use the
Organizer to transfer any custom views, reports, modules, etc. to a
temporary file so they can be restored once the new default Global is
generated.

If neither of the above works then the only other option I know of is to
re-install Project.

Hope this helps.
John