Date Range Report

K

Kim Godfrey

For my project, I select the filter: Date Range, to show me everything
between 10/24 thru 11/11. There is one task that has a start date of 11/11
and falls on this date range report. Is this filter designed to pick up end
dates that are the same as the start date?
 
J

John

Kim Godfrey said:
For my project, I select the filter: Date Range, to show me everything
between 10/24 thru 11/11. There is one task that has a start date of 11/11
and falls on this date range report. Is this filter designed to pick up end
dates that are the same as the start date?

Kim,
Take a look at the Date Range filter. You will see that it includes
tasks that start or finish ON the dates entered. However, I find the
wording used in the interactive input boxs is confusing and misleading.
I think it would be much clearer to have the two input boxes say
something like the following:
"Enter beginning date of range"?
"Enter ending date of range"?

If the task you mention is not appearing and the entered date range
includes the start or finish of that task, (and yes, it can be a zero
duration milestone that falls on the beginning or ending date), then
there must be something unique about the task but I'm not sure what. Off
hand I can't think of any circumstances wherein a task in the range
wouldn't be picked up by the filter.

John
Project MVP
 