Dates in a template

E

ejc

I am using MS Project 2002 in an enterprise.

Our company has created a template based upon processes that exist in our
framework. I like using the templates but when I create a new project from
the template and save it off it uses the dates from when the original
template was created.

I have two questions:
1. Was the template created incorrectly?
2. Is there a way to globally change the start date for the project instead
of having to go to multiple tasks and change the start dates?

Thank you.
 
M

Mike Glen

Or run the Adjust Dates macro from the Analysis tool bar to move any
constraints by the same amount.

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top