I am using MS Project 2002 in an enterprise.
Our company has created a template based upon processes that exist in our
framework. I like using the templates but when I create a new project from
the template and save it off it uses the dates from when the original
template was created.
I have two questions:
1. Was the template created incorrectly?
2. Is there a way to globally change the start date for the project instead
of having to go to multiple tasks and change the start dates?
Thank you.