K
Kokomojo
I want to use MS Project for budget tracking but I face a dilemma:
I'm told that I should enter tasks down to the DAY level, not more granular
than that. However, if I assign resources and rates, it will multiply by the
8 hr work day, even if a task will only take 1 hr to complete.
On the flipside, if I enter tasks down to the estimate HR level, it skews
the true project timeline. The application will assume that task B can take
place right after task A, even if the task wouldn’t technically start until
the following day.
Any insights? Thanks.
I'm told that I should enter tasks down to the DAY level, not more granular
than that. However, if I assign resources and rates, it will multiply by the
8 hr work day, even if a task will only take 1 hr to complete.
On the flipside, if I enter tasks down to the estimate HR level, it skews
the true project timeline. The application will assume that task B can take
place right after task A, even if the task wouldn’t technically start until
the following day.
Any insights? Thanks.