B
Binoy
Hi,
I have an issue with Microsoft Project rounding up/down (?) values for
work/actual work.
e.g.
Add a task with a duration of 20 days (Task type as fixed duration)
Create an assignment with resource 'A' for this task. (Rate defined as 1$/hr)
Enter Work as 100hrs. Units calculated as 61%
Enter Actual Work as 100.46 and click on Ok.
Notice that Work and Actual Work are changed to 100.47hrs (?). Units remains
61% and duration is 20 days.
I would like to know why the work/actual work was changed to 100.47 (from
100.46). What are the calculations that Project internally does to arrive at
this value?
Thanks
Binoy
I have an issue with Microsoft Project rounding up/down (?) values for
work/actual work.
e.g.
Add a task with a duration of 20 days (Task type as fixed duration)
Create an assignment with resource 'A' for this task. (Rate defined as 1$/hr)
Enter Work as 100hrs. Units calculated as 61%
Enter Actual Work as 100.46 and click on Ok.
Notice that Work and Actual Work are changed to 100.47hrs (?). Units remains
61% and duration is 20 days.
I would like to know why the work/actual work was changed to 100.47 (from
100.46). What are the calculations that Project internally does to arrive at
this value?
Thanks
Binoy