D
Darrel Bourne
I am currently working with an organization that tracks schedules by
duration, but wants to evaluate Earned Value based on work estimates for each
task. Each task is created as Fixed Work, and updates are made to the plan
by entering Actual duration for the task and Remaining duration for the task.
This approach works well except under the following scenario.
When a task takes LESS time than expected, the Work value gets
re-cacluclated even though the task is Fixed Work. Lets say it is a 5 day
task with a 5 day work effort. In the process that is used to update the
schedule, if the task is done in three days, the ACTUAL DURATION will be set
to 3 days and the REMAINING DURATION to 0 days. This sets DURATION to 3
days. However, the Work changes to 3 days as well. The reason for this is
that the UNITS do not change for the Resources. It stays at 100%. This does
not fit the model of a Fixed Work Task in my opinion. Now, if I change the
DURATION field to 3 days (as opposed to the ACTUAL and REMAINING DURATION
Fields), then the Units for the Resource DOES adjust to ensure that work is a
fixed 5 days. It jsut will not do this when I adjust DURATION using ACTUAL
DURATION and REMAINING DURATION.
For tasks that take longer than plan, everything works as it should.
Updating ACTUAL DURATION to 7 days in the example above leaves Work fixed at
5 days and adjusts the Resource Units. I do not undersatnad why this works
for the one scenario and not the other.
Any assistance on this wouldbe greatly appreciated.
duration, but wants to evaluate Earned Value based on work estimates for each
task. Each task is created as Fixed Work, and updates are made to the plan
by entering Actual duration for the task and Remaining duration for the task.
This approach works well except under the following scenario.
When a task takes LESS time than expected, the Work value gets
re-cacluclated even though the task is Fixed Work. Lets say it is a 5 day
task with a 5 day work effort. In the process that is used to update the
schedule, if the task is done in three days, the ACTUAL DURATION will be set
to 3 days and the REMAINING DURATION to 0 days. This sets DURATION to 3
days. However, the Work changes to 3 days as well. The reason for this is
that the UNITS do not change for the Resources. It stays at 100%. This does
not fit the model of a Fixed Work Task in my opinion. Now, if I change the
DURATION field to 3 days (as opposed to the ACTUAL and REMAINING DURATION
Fields), then the Units for the Resource DOES adjust to ensure that work is a
fixed 5 days. It jsut will not do this when I adjust DURATION using ACTUAL
DURATION and REMAINING DURATION.
For tasks that take longer than plan, everything works as it should.
Updating ACTUAL DURATION to 7 days in the example above leaves Work fixed at
5 days and adjusts the Resource Units. I do not undersatnad why this works
for the one scenario and not the other.
Any assistance on this wouldbe greatly appreciated.