Sorry, I meant to write DAYS in stead of hours.
So expressing more specifically, thanks Steve, is there a way of
expressing the workload in DAYS rather than hours.
Duration is not my first concern.
"Steve House" <sjhouse at hotmail dot com> wrote in message
Workload and duration are two different things entirely. Workload
is effort (work) and is entered in man-hours. Duration is
work-hour calendar time between start and finish.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
"Jan de Wit" <s> wrote in message
Thanks Jan,
No, that doesn't help much I am afraid.
I want to enter the workload in hours, not only show it in the
summary.
Any other ideas?
Cheers, Jan
"Jan De Messemaeker" <jandemes at prom hyphen ade dot be> wrote in
message Hi,
Project doesn't count in hours, it always, inevitably counts in
minutes, sorry :-(
But you can enter durations in days (that is even the default)
and if you want to show Work in days, Tools, Options, Schedule,
has an option for that.
Hope this helps,
--
Jan De Messemaeker
Microsoft Project MVP
http://users.online.be/prom-ade
"Jan de Wit" <s> wrote in message
Project 2003 counts with 8/h per day.
However, I am not interestd in calculating in hours, I want to
set up a project in days. How to go about?