"Days To-Go"

I

iron

I was asked recently to provide a "Days To-Go" field. I thought I could
create a field that would look something like: %Complete<>0 and
(Duration*(1-%Complete)). Well, I get a very large number and can't seem to
get it to work. Does anyone have suggestions?
 
J

Jan De Messemaeker

Hi,

Duration is expressed in minutes.
The good news is, use the remaining duration field.
HTH
 
R

RK

% complete and % work complete are diffrent .

%complete = the % of "duration" complete
and
% work complete = the % of "work (hours)" complete

So to answer your question, in the equation you used, if you need the amount
of duration then use %complete and if you need the amount of work(hour) use %
work complete

Please note that you will have to manually assess the "Days to go" if some
one is asking for the elapsed days by refering the resource alander.

Hppe this helps.

-Ratheesh
 