Leveling delays Tasks until there is no over-allocation, if it can.
First try using Leveling without the options checked, so with no task
splitting, assignment adjustment etc.
The Leveling options are eaiser to understand and apply after first getting
on top of vanilla Leveling.
Check especially the effect of adjusting Task Priority to force leveling to
delay one Task instead of the other if the MSP solution did not match your
preferences.
Most importantly, establish what Leveling does and what it does not do.
Leveling delays Tasks to remove over-allocation, and nothing else. It
doesn't change Work or assignment units or Duration. Many people using MSP
are a bit confused about what Leveling means, what it is supposed to be for
and what it does.
MSP will only be able to find a solution for the Resource over-allocation if
one exists. If you over-allocate Resources too heavily and/or prevent Tasks
from moving by setting Date Constraints MSP will not be able to find a
Leveling solution. Also, assigning Resources to Summaries will usually
prevent a solution.
Leveling can be used in a number of ways. It can move the Tasks so that the
Resources are not over-allocated, or it can tell you how severe the
over-allocation is so that you can reconsider and re-do your Resource
assignments.
Of course, if Leveling delays Tasks which are already on the Critical Path,
the overall project duration gets longer.
Also, it is possible for Leveling to delay Tasks which are not Critical.
Leveling causes Tasks to be moved to earliest possible start dates which do
not depend on just the durations and the predecessor links, so the critical
path is lost.
This then leaves you with a need to find the longest path, which is not so
evident in MSP but which standard in P3.
The un-leveled version of the project plan is short but not feasible due to
Resource limitations, while the Leveled version is longer but at least it is
feasible.
You have to balance out these conflicting objectives.
Leveling is a powerful tool. Projects should not start if there is
unresolved Resource over-allocation.
Trevor Rabey 0407213955 61 8 92729485 PERFECT PROJECT PLANNING
www.perfectproject.com.au