Define defult filtered for "all tasks"

F

fitus

When I open project, the filtered is always on "critical",
How can I change the defult filtered for "all tasks".
 
J

JulieS

Hi Fitus,

I am assuming from your post that this the critical filter is on all new
projects. Create a new project. Choose View> More Views and select the
current view. Click the Edit button and set the filter to "All Tasks". Click
OK. In the More Views dialog box click the Organizer button. On the Views
tab copy the view from the current file to the Global.MPT file. Click the
"Yes" button to replace the view in Global.MPT.

Hope this helps. Let us know how you get along.

Julie
 