Hello Jeffrey,
Thanks for the additional clarification that you are still working on
the scheduling (planning) of your project not the tracking part. I see
you have been corresponding with Jim as well concerning the leveling
delay field. Like Jim, I cannot reproduce what you report with the
leveling delay field in the Resource Allocation view > Leveling Gantt
with Delay table applied.
What version of Project are you using and what is the Service Pack Level
(See Help > About Microsoft Project for SP information.)
You can also delay the assignment for individual resources on a task if
that would be helpful. From the Gantt chart view, split your screen
(Window > Split) to show the Task Form in the bottom pane. Click to
activate the bottom pane if necessary and then choose Format > Details
and select Resource Schedule. You'll see two "delay" fields for each
assignment -- leveling delay and assignment delay. Those two fields can
also be added to the Task Usage or the Resource Usage view. See if the
assignment delay field works better for you than the leveling delay
field.
You may also delay a resource's work on a task by editing the work in
the timescaled (right side) portion of the Task Usage or Resource Usage
view. Simply enter zeros on the days you want to postpone the start of
the work.
As far as rating -- sorry, that one I can't answer as I don't usually
use the web to get to this newsgroup. I appreciate you wanting to rate
the answer though -- the important thing is helping you get to the
bottom of the problem
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project