Deleting Weekend Dates from Calculated Timeline

C

Carmen

Is there a way to have the calendar not count weekend dates when computing
the length of a project?
 
J

John

Carmen said:
Is there a way to have the calendar not count weekend dates when computing
the length of a project?

Carmen,
The value in the Duration field (i.e. length of project) is by default
the working time. As such it does NOT include weekends and other
non-working time. The only time this will not be true is if you have
entered duration values in elapsed time (e.g. 30ed).

Note that the Gantt Chart timeline WILL show non-working time.

Hope this helps.
John
Project MVP
 