Carmen,
The value in the Duration field (i.e. length of project) is by default
the working time. As such it does NOT include weekends and other
non-working time. The only time this will not be true is if you have
entered duration values in elapsed time (e.g. 30ed).
Note that the Gantt Chart timeline WILL show non-working time.
Hope this helps.
John
Project MVP
Ask a Question
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.