Hi,

When we use Deliverables in Project 2007, we can link the deliverable to a
specific task. My question is how can we know in the dependency project that
the task is completed and that the deliverable is done\completed? Is there a
way through the deliverables mechanism to indicate that it is indeed done?
Thanks for your help

Zach
--
 
M

Mike Glen

Hi Zach,

If you're using Project Pro & Server, try posting on the server newsgroup.
Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and
other useful Project information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 