M
Mani
Hi
is there a suggested best practice to create dependencies when building the
plan. The issue that I am struggling with is if it is correct to create
dependencies between the summary task A and summary task B even though tasks
A.1 and A.2 and A.3 are all linked and separate from B.1 and B.2, etc which
are also linked, within their own subtask.
is there a suggested best practice to create dependencies when building the
plan. The issue that I am struggling with is if it is correct to create
dependencies between the summary task A and summary task B even though tasks
A.1 and A.2 and A.3 are all linked and separate from B.1 and B.2, etc which
are also linked, within their own subtask.