C
Carolyn in Fredericton NB
Hello
My interpretation of setting up dependencies between tasks was to only link
those that were truly dependent; e.g., Task B can only start once Task A is
done. If you have 2 tasks, C and D, that represent work (example, code
procedure 1 and code procedure 2) that are not dependent on each other, but
are tasks to which you would likely assign the same resource, you should not
link them, but rather assign the resource to both, and use resource levelling
to take care of the overallocation. I know that often people will assign
dependencies between tasks that are not "true" dependencies to prevent a
resource from being overallocated, but if circumstances arose whereby you
could assign a second Resource to Task D, it would schedule a start date to
Task D based on the first resource finishing Task C, rather than scheduling
Task D to start as soon as possible. Basically, i am trying to only link
tasks that are really only truly dependent on each other, and using resource
levelling to handle the scheduling.
Am I off base?
My interpretation of setting up dependencies between tasks was to only link
those that were truly dependent; e.g., Task B can only start once Task A is
done. If you have 2 tasks, C and D, that represent work (example, code
procedure 1 and code procedure 2) that are not dependent on each other, but
are tasks to which you would likely assign the same resource, you should not
link them, but rather assign the resource to both, and use resource levelling
to take care of the overallocation. I know that often people will assign
dependencies between tasks that are not "true" dependencies to prevent a
resource from being overallocated, but if circumstances arose whereby you
could assign a second Resource to Task D, it would schedule a start date to
Task D based on the first resource finishing Task C, rather than scheduling
Task D to start as soon as possible. Basically, i am trying to only link
tasks that are really only truly dependent on each other, and using resource
levelling to handle the scheduling.
Am I off base?