T
Tim
Forgive me, but I am new to MS Project...
I have a task that I need to set up that has a specific start date and a
specific end date. There are several sub-tasks that each have the same 5
sub-tasks below them.
Instead of listing actual resources, I have resources called "Task 1
Workers," "Task 2 Workers," etc. My goal is to determine how many people I
need to allocate to each group ("Task 1 Workers," "Task 2 Workers," etc.) to
effciently complete the project on time.
Currently I have each task set up as a start - finish task, have guessed on
the number of resources needed, and leveled the project. I was able to come
up with a decent guess, but I don't feel like my resources are being used
efficiently and would like Project to calculate how many people I need to
assign to each group ("Task 1 Workers," etc.) to get the job done on time.
My Questions are:
Is this possible in Project?
How do I set up the project to accomplish this?
Am I at all on the right track, or am I way off base?
Thanks in advance to all.
I have a task that I need to set up that has a specific start date and a
specific end date. There are several sub-tasks that each have the same 5
sub-tasks below them.
Instead of listing actual resources, I have resources called "Task 1
Workers," "Task 2 Workers," etc. My goal is to determine how many people I
need to allocate to each group ("Task 1 Workers," "Task 2 Workers," etc.) to
effciently complete the project on time.
Currently I have each task set up as a start - finish task, have guessed on
the number of resources needed, and leveled the project. I was able to come
up with a decent guess, but I don't feel like my resources are being used
efficiently and would like Project to calculate how many people I need to
assign to each group ("Task 1 Workers," etc.) to get the job done on time.
My Questions are:
Is this possible in Project?
How do I set up the project to accomplish this?
Am I at all on the right track, or am I way off base?
Thanks in advance to all.