J
Joe
I know I am missing something here, I am hoping someone
can explain in simple terms.
In general terms and at a given point in a project, if the
BCWP is less than the BCWS, then I understand that the
project may have been underestimated because we are now
behind schedule. What I am struggling with is the ACWP,
wouldn't this be the same as the BCWP? For example, If we
planned to work 40 hours by today at $1.00 an hour, but we
only worked 32 hours (or $32), then wouldn't the BCWP and
ACWP both be $32? How and when would ACWP and BCWP be
different? I know they can and will be, I just don't
fully understand how and why? One thing I am thinking is
if someone works overtime to make up for lost time that
would drive up the ACWP, but maybe not necessarily the
BCWP. Can some explain a simple scenario in plain English?
Thanks!
can explain in simple terms.
In general terms and at a given point in a project, if the
BCWP is less than the BCWS, then I understand that the
project may have been underestimated because we are now
behind schedule. What I am struggling with is the ACWP,
wouldn't this be the same as the BCWP? For example, If we
planned to work 40 hours by today at $1.00 an hour, but we
only worked 32 hours (or $32), then wouldn't the BCWP and
ACWP both be $32? How and when would ACWP and BCWP be
different? I know they can and will be, I just don't
fully understand how and why? One thing I am thinking is
if someone works overtime to make up for lost time that
would drive up the ACWP, but maybe not necessarily the
BCWP. Can some explain a simple scenario in plain English?
Thanks!