N
Neill
I've got two tasks with the same duration in two separate projects that start
6/2/2005 but they finish on dates that are weeks apart (4/20 vs 5/3). They
both use the Standard Calendar and are even across the same period. I checked
the calendars and couldn't find any differences. The Pred/Succ are the same
too. Any suggestions?