K
Kesavan
Hi
I want to assign different work hours for different resources. Say for
eg. R1 has productivity of 7 hr/day, R2 has 6 hr/day. When I assign R1(100%)
to a task (Fixed work based) which takes say 21 hrs, the duration should be 3
days. For the same number of hours, R2 will take 3.5 days.
How do I achieve this?
I tried creating two different calendars one with working hours of 8: 12
and 1:4
and the other with working hours of 9:12 and 1:4. It does not reflect the
way I was expecting it in the Gantt Chart.
Any suggestions how I do this?
I want to assign different work hours for different resources. Say for
eg. R1 has productivity of 7 hr/day, R2 has 6 hr/day. When I assign R1(100%)
to a task (Fixed work based) which takes say 21 hrs, the duration should be 3
days. For the same number of hours, R2 will take 3.5 days.
How do I achieve this?
I tried creating two different calendars one with working hours of 8: 12
and 1:4
and the other with working hours of 9:12 and 1:4. It does not reflect the
way I was expecting it in the Gantt Chart.
Any suggestions how I do this?