D
DS
I'm using MS Project 2003. I have 2 tasks that run simultaneosly and are
unrealted (no relationship between them) they are set with a duration of 7
days or 56 working hours using Project default settings. In fact they would
be 7 days if I oly used the standard 8 hr calendar. Both are displayed
properly on the Gantt for 7 working days. Depending on the project, we
sometimes work 10 or 12 hr days. So, I have created 2 new calendars. One is
a 12hr day for 7 days a week. The second is 10 hr days for 6 days a week.
When I assign the calendars to the tasks, the Gantt bars shorten, but
duration stays the same and work is listed as 0 hrs. Worse, when I assign a
resource, both Gantt bars go back to full 7 day length and work displays as
56 hrs.
I need the Gantt and Duration to show that with the 10 hr work day and 1
resource that this task is now 5.6 days? Can this be done? Right now it
seems as if I need to manually calculate my duration and it's causing alot of
grey hair.
Thanks in advance.
unrealted (no relationship between them) they are set with a duration of 7
days or 56 working hours using Project default settings. In fact they would
be 7 days if I oly used the standard 8 hr calendar. Both are displayed
properly on the Gantt for 7 working days. Depending on the project, we
sometimes work 10 or 12 hr days. So, I have created 2 new calendars. One is
a 12hr day for 7 days a week. The second is 10 hr days for 6 days a week.
When I assign the calendars to the tasks, the Gantt bars shorten, but
duration stays the same and work is listed as 0 hrs. Worse, when I assign a
resource, both Gantt bars go back to full 7 day length and work displays as
56 hrs.
I need the Gantt and Duration to show that with the 10 hr work day and 1
resource that this task is now 5.6 days? Can this be done? Right now it
seems as if I need to manually calculate my duration and it's causing alot of
grey hair.
Thanks in advance.