Difficulty exanding/collapsing summary level tasks

P

PattiTechWriter

All of a sudden I can't expand or collapse my summary level tasks...its like
the project is frozen. Has this happened to anyone else? I'd like to know
what I did to cause this so I don't repeat it. And Is the damage reversable?

Patti
 
M

Mike Glen

Hi Patti,

Welcome to this Microsoft Project newsgroup :)

Which version do you have and have you installed the latest Service Release?

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 
P

PattiTechWriter

Hi Mike...I'm running 2003, SP1

Mike Glen said:
Hi Patti,

Welcome to this Microsoft Project newsgroup :)

Which version do you have and have you installed the latest Service Release?

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 
P

PattiTechWriter

Also, the difficulty expanding/collapsing occurs while in Gantt Chart view
and not in Tracking Gantt view...Does anyone know why? I always used Gantt
Chart before yesterday without issue.
 
J

Jim Spiller

Might be sorted. Go to Project-Sort-by ID.



PattiTechWriter said:
Also, the difficulty expanding/collapsing occurs while in Gantt Chart view
and not in Tracking Gantt view...Does anyone know why? I always used
Gantt
Chart before yesterday without issue.
 
P

PattiTechWriter

Thank you Jim! You rock!

I don't know what i did to mess up the schedule, but thanks to you, it works
now!
 