disable row in PWA's timesheet view

S

satya_v

Is there anyone knows how to disable actual work and remaining work
fields in timesheet for several (not all) tasks?
In our project plan, there are several tasks with Finish-to-start
dependencies. The project manager assigned resources to the tasks and
published them in Project Server.
We use Actual and remaining work as progress tracking. The problem is:
the resource can fill out the actual and remaining work even when the
previous task is not finished yet. We want to disable the field in the
grid for a task if its predecessor is not completed.

Any ideas would be really appreciated.

thanks in advance,
Satya
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top