C
Copper
I would like to display two columns for durations for a given task that is 8
working days.
The project uses the standard calendar, i.e., Saturdays and Sundays are not
working days.
For example:
Task A - Start: 3/18/05 8 working days duration Finish 3:29/05
Duration in Project displays 8 days.
How do I set up a field that will display the elaped duration of 11 days. I
have tried to use formulas for Duration 1 such as subtracting the start date
from the finish date but have had no luck.
I would like it to display as below:
Duration Duration1
8d 11d
working days.
The project uses the standard calendar, i.e., Saturdays and Sundays are not
working days.
For example:
Task A - Start: 3/18/05 8 working days duration Finish 3:29/05
Duration in Project displays 8 days.
How do I set up a field that will display the elaped duration of 11 days. I
have tried to use formulas for Duration 1 such as subtracting the start date
from the finish date but have had no luck.
I would like it to display as below:
Duration Duration1
8d 11d