cbd
I have a 'special situation'.
I have formatted the bar styles of the Gantt Chart so that I can see the
milestones in the rolled-up summary tasks as diamonds. There are dependencies
between the milestones of one summary task and the milestones of another
summary task.
What I would like, is that the link lines are also displayed between the
milestones in the summary task bar. This way I can see the dependencies, also
when the subtasks (and milestones) are hidden.
Is this possible in any way?