Display of Overtime Work

I

ITSDesigner

I have resources that work on several different projects. I assigned the
resource to a 40 work week. On the Resouce Usage View, some of the resources
have fewer than 40 hours per week, but are shown in red. why is this and how
can I change it?
 
A

andrewandrew

If they are scheduled at more than 8hrs per day (or whatever their calendar
says their availability is per day) or more than 1hr per available hour, then
overallocations are reported on the usage view in red, like you're seeing.
Zoom in and it should become clearer.
 
M

Mike Glen

Hi Steve,

Welcome to this Microsoft Project newsgroup :)

Please see FAQ #28 - Resource Levelling Does Not Remove Overallocation
and/or #34 - Overallocation Occurring In Less Than One Day.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
 
I

ITSDesigner

Thanks, this helps a lot.
--
Steve


Mike Glen said:
Hi Steve,

Welcome to this Microsoft Project newsgroup :)

Please see FAQ #28 - Resource Levelling Does Not Remove Overallocation
and/or #34 - Overallocation Occurring In Less Than One Day.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
 