Displaying duration in hours

D

David Morrison

I've entered some time for duration in hours and some in minutes. How can I
get Project to display everything in hours regardless of how I enter it?
I've already tried going to Tools|Options|Schedule tab|Duration is entered
in "Hours" but that didn't do it.
 
D

Dale Howard [MVP]

David --

Try Tools - Macro - Macros then click the Format Duration macro and click
Run. Select the Duration units and click OK. Hope this helps.
 
D

David Morrison

Worked like a charm. Thanks!

Dale Howard said:
David --

Try Tools - Macro - Macros then click the Format Duration macro and click
Run. Select the Duration units and click OK. Hope this helps.