displaying summary task info

J

jesse mauch

In, for example, calendar view I wish to be able to see
which summary task a subtask is coming from. Does anyone
no how to have this info displayed?
 
M

Mike Glen

Hi Jesse,

Welcome to this Microsoft Project newsgroup :)

There are no specific settings for this. You could set the Format/Bar
Styles.../Text cell to read WBS,Name and this should put the WBS number in
front of the task Name to help you identify the structure.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top