Just started using Project 2003 at work. Put tasks into Gantt chart and
clicked "Calendar View." The calendar is displaying October 1987. How can I
fix this - besides scrolling forward 18 years?
 
M

Mike Glen

Hi ackie,

Welcome to this Microsoft Project newsgroup :)

Have you set Project/Project Information/Project Start Date?

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 
J

JulieS

Hi Jackiebp,

I haven't seen this one before but here are a couple of suggestions to check:

1) Are you running SP-1 for MS Project 2003? Check Help > About Microsoft
Project to see.

If you have not installed SP-1 you can download it from
http://www.microsoft.com/downloads/...73-e58f-4f42-b76d-6b565a45cdc3&displaylang=en

2) What is the start date of your Project? Check Project>Project Information.

3) Have you inadvertantly added a task that has a start date in 1987? Sort
the Gantt chart by Start Date to check.

Hope this helps. Let us know how you get along.