We imported an old file into Project when this started occuring, but I have
since uninstalled and reinstalled the application, but it still is not
working.
I am attempting to create several tasks in Project and then link them so
they are dependent on each other. Once I link them they do not move out to
show the dependency on the previous one. Any thoughts as to why?
-- SteelBee
 
M

Mike Glen

Hi SteelBee,

Welcome to this Microsoft Project newsgroup :)

Tools/Options.../Calculcation tab and set Calculation to Automatic.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 
J

Jan De Messemaeker

......
And/Or make sure the tasks are 0% completed
And/or make their constraints "as soon as possible"
hth
 
S

steelbee

Thank you, Thank you!!
That solved it. Thanks for the helpful site about Project too. You are a
life saver.
 