duplicate tasks in resource usage report

E

eng master

I continue to receive duplicate tasks along with work in the resource usage
report. II maintain a master project with linked sub projects. The tasks
duplicated appear randomly.
 
B

Brian K - Project MVP

eng said:
I continue to receive duplicate tasks along with work in the resource usage
report. II maintain a master project with linked sub projects. The tasks
duplicated appear randomly.

insert the Project field and see if the duplicate tasks come from
different projects. If so then you might have tasks with the same name in
different projects.
 