Yes it does. Unfortunately, it also creates a constraint "Finish No Earlier
Than" which is not normally a good thing and decreases your %Complete. Here
are two procedures that will avoid creating the unneeded constraint:
1. Instead of changing the Finish date, increase the duration until the
finish date lands where you want it to. This is the easiest, remember to
keep your %Complete by rekeying it.
2. Some people prefer to key the finish date. If you do, you need to also
re-adjust the %Complete. In addition, open the task information dialog box
(by double clicking the task), pull the advanced tab and change the
constraint type to "As Soon As Possible" or whatever it used to be. As long
as there is a %Complete >0% your will get what you want.
--
If this post was helpful, please consider rating it.
Jim
It''s software; it''s not allowed to win.
Visit
http://project.mvps.org/ for FAQs and more information
about Microsoft Project