Duration calculations

D

Dek809

Hi All,

Grateful of any assistance in what is probably a simple answer! I have a
task that has Date1, Date2, Date3, Date4 and Date5 columns. If Date1 is say
31 Mar 09 and Date5 is 25 Jun 09, how can I calculate the duration? Date2,
Date3 and Date4 will be in-between 1 and 5. Many thanks in advance Guys.

Regards,

Dek
 
J

Jack Dahlgren

Insert another date column and use the ProjDateDiff function in a formula
there. It will determine the difference between the two dates taking into
account the project working calendar - giving you the duration between them.

-Jack Dahlgren
 