duration changes when entering actual work in Project 2003

A

Andy

I am trying to update actual work perfomed in the "Resource Usage Sheet".
The start and/or end dates are changing. How can I fix this? I have all the
tasks marked as "fixed Duration" and have set caluction options to manual,
yet the dates still change

?????
 
M

Mike Glen

Hi Andy,

Welcome to this Microsoft Project newsgroup :)

When you enter Actual Work, you need also to enter the Remaining Work,
whence Project will meet your requirements.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 