A
Allison
I am confused by my duration not changing. I have a task that has a 5 day
duration, and the task type of Fixed Unit, effort driven. I then assign
resource X to that task, and resource X only works part time, and I have
modified that resources' calendar to reflect their part-time status. I have
been told to keep their units on the resource sheet to 100%, and make changes
for part-time employees by using the calendar to help Project schedule
correctly.
However, when I assign that resource to the 5 day duration task, the hours
worked is 40h (as expected), the start and finish dates end up being 14 days
apart due to 2 weekends (as expected), but the duration remains at 5 days.
Why? Is it because duration = calendar work hours per day (8) * # of days?
Can I add a field that shows days lapsed vs. duration if I am correct?
Thanks...hope this makes sense.
duration, and the task type of Fixed Unit, effort driven. I then assign
resource X to that task, and resource X only works part time, and I have
modified that resources' calendar to reflect their part-time status. I have
been told to keep their units on the resource sheet to 100%, and make changes
for part-time employees by using the calendar to help Project schedule
correctly.
However, when I assign that resource to the 5 day duration task, the hours
worked is 40h (as expected), the start and finish dates end up being 14 days
apart due to 2 weekends (as expected), but the duration remains at 5 days.
Why? Is it because duration = calendar work hours per day (8) * # of days?
Can I add a field that shows days lapsed vs. duration if I am correct?
Thanks...hope this makes sense.